Revision summary
Wind still leads installed renewables; solar is the fastest-growing slice after parks and auctions. The headline target is 175 GW by 2022, led by 100 GW solar and 60 GW wind. Paris-era INDC adds a 40 per cent non-fossil capacity share by 2030. The National LED programme through EESL cuts peak demand, bills, and carbon. Supply targets and efficient lighting succeed together only if the grid and product quality hold.
Model answer
Introduction
India still runs a large share of its grid on coal, yet sunlight, wind, biomass, and small hydro are no longer side experiments. After the revised Jawaharlal Nehru National Solar Mission and the 175 gigawatt renewable target for 2022, capacity and auctions have moved fast. The question asks for that status and those targets, and then for a short account of the National Programme on Light Emitting Diodes (LEDs), which cuts demand even as new green supply is built.
Body
Current status
- Wind is still the largest renewable slice of installed capacity, concentrated in Tamil Nadu, Gujarat, Maharashtra, Rajasthan, and Karnataka, with a shift from feed-in tariffs toward competitive bidding.
- Solar has grown sharply since 2014–15 through solar parks, rooftop policy, and reverse auctions that brought tariffs down; deserts, canals, and rooftops are the three main sites.
- Biomass, bagasse cogeneration, waste-to-energy, and small hydro add smaller but useful megawatts, especially where a factory already has fuel or a hill stream can take a run-of-river plant.
- Large hydro is counted separately from the Ministry of New and Renewable Energy basket, yet it remains a major non-fossil source for the grid.
- Manufacturing, storage, and transmission still lag generation announcements: solar cells and modules are import-heavy, and renewable-rich States face evacuation and must-run disputes with distribution companies.
Targets to be achieved
- The Union target of 175 GW of renewable capacity by 2022 is the working number: 100 GW solar (utility plus rooftop), 60 GW wind, 10 GW bio-energy, and 5 GW small hydro.
- India’s Intended Nationally Determined Contribution after Paris (2015) pledges that about 40 per cent of installed electric power capacity will come from non-fossil sources by 2030, and that emissions intensity of GDP will fall 33–35 per cent from 2005 levels by 2030.
- The International Solar Alliance, announced at Paris and hosted by India, is a diplomatic target as well as a technology club for sun-rich countries.
- State renewable purchase obligations, green corridors, and ultra-mega solar parks are the instruments meant to turn the 175 GW figure into wires and meters, not only a speech.
Why the targets matter
- They reduce the coal import and air-pollution bill, and they hedge a future carbon constraint on exports and climate finance.
- They can create installation, operation, and small-manufacturing jobs if Make in India on cells, inverters, and towers actually happens.
- They fail if land, forest clearance, and unpaid discom dues stall plants, or if the grid cannot absorb daytime solar.
National Programme on LEDs
- The programme, delivered mainly through Energy Efficiency Services Limited, aggregates demand so households and urban local bodies buy LED lamps and street lights at a low price instead of incandescent or sodium lamps.
- Unnat Jyoti by Affordable LEDs for All (UJALA) puts efficient bulbs in homes; the Street Lighting National Programme replaces municipal lighting.
- Importance is threefold: peak load falls, so fewer peaking plants and less diesel; household and municipal bills fall; carbon and local air pollution fall for the same lumen.
- It is the cheapest “renewable” megawatt because a unit not consumed need not be generated. It also builds a domestic LED manufacturing and assembly chain.
- Limits: quality and warranty must be policed, or cheap failures will send users back to old lamps; street-light savings need honest metering by municipalities.
Flow diagram
flowchart TD RE[Renewable status wind solar bio SHP] --> TGT[175 GW by 2022] TGT --> INDC[40 percent non-fossil by 2030] LED[National LED programme UJALA street lights] --> DEM[Lower peak and bills] TGT --> GRID[Green corridors auctions] DEM --> GRID
Conclusion
India’s renewable story in 2016 is a real rise in wind and solar against a still-coal grid, judged against the 175 GW (2022) and 40 per cent non-fossil (2030) marks. The LED programme is the demand-side twin of that supply push: cheaper light, lower peak, and less carbon. Targets will count only when evacuation, discom payments, and lamp quality keep up with auctions and bulb distribution.
Quick related
Students also ask
-
To what factors can be the recent dramatic fall in equipment cost and tariff of solar energy be attributed? What implications does the trend have for thermal power producers and related industry?
Next question on this syllabus topic (2015 · Q9). View answer →
-
Does the 175 GW target include large dams?
No. It is the MNRE renewable basket. Large hydro is additional non-fossil capacity in the wider INDC arithmetic.
-
Why discuss LEDs in a renewable-energy question?
Because a unit saved by an efficient lamp is a unit the coal or gas plant need not generate, and it cuts the peak that renewables alone do not always cover.
PYQ trend
When UPSC asked this
Related PYQs from other years, newest first. Open a question to read it.
-
2024 · Q6 · GS III · 10 marks
What is the technology being employed for electronic toll collection on highways. What are its advantages and limitations? What are the proposed changes that will make this process seamless? Would this transition carry any potential hazard? -
2022 · Q1 · GS III · 10 marks
Why is Public Private Partnership (PPP) required in infrastructural projects ? Examine the role of PPP model in the redevelopment of Railway Stations in India. -
2021 · Q12 · GS III · 15 marks
"Investment in infrastructure is essential for more rapid and inclusive economic growth. "Discuss in the light of India's experience. -
2020 · Q16 · GS III · 15 marks
Describe the benefits of deriving electric energy from sunlight in contrast to the conventional energy generation. What are the initiatives offered by our Government for this purpose? -
2018 · Q1 · GS III · 10 marks
"Access to affordable, reliable, sustainable and modern energy is the sine qua non to achieve Sustainable Development Goals (SDGs)".Comment on the progress made in India in this regard. (150 Words, 10 Marks). -
2018 · Q16 · GS III · 15 marks
With growing energy needs should India keep on expanding its nuclear energy programme? Discuss the facts and fears associated with nuclear energy. (250 Words, 15 Marks). -
2017 · Q3 · GS III · 10 marks
Examine the developments of Airports in India through Joint Ventures under Public-Private Partnership(PPP) model. What are the challenges faced by the authorities in this regard. -
2015 · Q9 · GS III · 12 marks
To what factors can be the recent dramatic fall in equipment cost and tariff of solar energy be attributed? What implications does the trend have for thermal power producers and related industry?
More from this topic
Q6 · UPSC Mains 2025 · GS III · 10 marks
How can India achieve energy independence through clean technology by 2047? How can biotechnology play a crucial role in this endeavour?
Infrastructure
India still imports most of its crude, so 2047 independence means much lower import intensity, not a sealed border. Clean electricity from solar, wind, storage and nuclear, plus green hydrogen and efficiency, are the main path. Electric mobility cuts oil only if the grid is cleaner. Biotechnology helps through biogas, second-generation ethanol from residue, industrial enzymes and less energy-intensive farming. Fuel-from-food is a poor version of that biotech role.
Q5 · UPSC Mains 2025 · GS III · 10 marks
The fusion energy programme in India has steadily evolved over the past few decades. Mention India's contributions to the international fusion energy project - International Thermonuclear Experimental Reactor (ITER). What will be the implications of the success of this project for the future of global energy?
Infrastructure
Fusion joins light nuclei and could, in theory, give large low-carbon power without a fission-style chain reaction. ITER in France is the global experiment; India is a member supplying about a tenth of in-kind components such as the cryostat and cooling systems. Indian tokamaks and the Institute for Plasma Research built the domestic base. ITER success would prove the physics, not deliver cheap power in 2030. The climate implication is a possible later baseload, beside renewables that are needed now.
Q6 · UPSC Mains 2024 · GS III · 10 marks
What is the technology being employed for electronic toll collection on highways. What are its advantages and limitations? What are the proposed changes that will make this process seamless? Would this transition carry any potential hazard?
Infrastructure
Electronic toll collection on Indian highways uses RFID FASTag, settled on NPCI’s NETC rail. Advantages are less cash leakage, less idling and a digital trail. Limitations are failed reads, double deduction, lane mixing and plaza-only coverage. The proposed seamless step is GNSS-based free-flow tolling, often with ANPR, so the car need not stop. The transition hazard is continuous location tracking, spoofing and hard-to-dispute bills unless data rules and refunds are strong.
Toppers' copies
Toppers' copies for this question will be uploaded soon.