Q6 · UPPSC PCS Mains 2021 · GS III · 8 marks · ~125 words in the hall · 1 min read

← Q5 Q7 →

What are the constraints in the development of infrastructural projects in Uttar Pradesh? Explain the steps taken by the State Government to remove the constraints.

Topic: Economic planning and NITI Aayog. Syllabus: Economic planning in India: objectives and achievements. Role of NITI Aayog, Pursuit of Sustainable Development Goals (SDGs). Same official PYQ from year-wise 2021 and Economic planning and NITI Aayog.

Revision summary

UP infrastructure stalls on land, environment clearances, DPR delay, municipal finance, and last-mile power. UPEIDA expressways (Agra–Lucknow, Purvanchal, Bundelkhand, Ganga) cut logistics time. Jewar airport, Defence Industrial Corridor, and Lucknow–Kanpur–Agra Metro are named large projects. Nivesh Mitra, Invest UP, UPSIDA land banks, and PM Gati Shakti pack approvals. Files still win if land records and city finance stay weak.

Model answer

Introduction

Uttar Pradesh needs roads, power, airports, and urban services for a large, dense population. Projects stall on land, clearances, finance, and contractor capacity. The State’s reply has been land banks, a single window, and a named expressway-and-airport push.

Body

Constraints

  • Land acquisition, forest and environmental clearances, and delayed detailed project reports stretch timelines, especially in peri-urban and Bundelkhand or Tarai tracts.
  • Weak municipal and utility finance, right-of-way fights, and last-mile power quality slow industrial parks even after a ribbon is cut.
  • Contractor capacity, utility shifting, and, in some pockets, law-and-order risk raise cost overruns on PPP and EPC jobs.

Steps taken

  • Uttar Pradesh Expressways Industrial Development Authority built Agra–Lucknow, Purvanchal, Bundelkhand, and Ganga expressways to cut logistics time and to seed industrial corridors.
  • Noida International Airport at Jewar, Defence Industrial Corridors, and Metro in Lucknow, Kanpur, and Agra are the named large projects.
  • Nivesh Mitra single window, Invest UP, UPSIDA land banks, and the State node of PM Gati Shakti aim to pack land, power, and approvals so that a project does not die in files.

Flow diagram

flowchart TD
  X[Constraints] --> L[Land clearances finance]
  X --> U[Last mile power PPP]
  S[UPEIDA expressways Jewar] --> F[Faster logistics]
  N[Nivesh Mitra Gati Shakti] --> F
  L --> T[Project delay]
  F --> T

Conclusion

Land, clearances, finance, and last-mile utilities are the main constraints. UPEIDA expressways, Jewar airport, metros, Nivesh Mitra, and Gati Shakti are the State’s removal tools; they work only if land records and municipal finance catch up.

Quick related

Students also ask

PYQ trend

When UPSC asked this

Related PYQs from other years, newest first. Open a question to read it.

  1. 2021 · Q1 · UPGS3 · 8 marks

    Discuss the Digital India Programme of India.

    View answer →

  2. 2021 · Q2 · UPGS3 · 8 marks

    Examine the impact of globalization on employment of formal sector of India.

    View answer →

  3. 2021 · Q4 · UPGS3 · 8 marks

    What is Sustainable Development Goal–2030? Discuss the relevance of different agendas associated with it.

    View answer →

  4. 2021 · Q11 · UPGS3 · 12 marks

    What is National Policy in India related to Artificial Intelligence? Explain in detail.

    View answer →

  5. 2021 · Q19 · UPGS3 · 12 marks

    Discuss the kinds and functions of civil defence. How much is it effective in Uttar Pradesh? Explain.

    View answer →

  6. 2020 · Q1 · UPGS3 · 8 marks

    What do you understand by "leaving no one behind" with reference to sustainable development goals?

    View answer →

  7. 2020 · Q2 · UPGS3 · 8 marks

    What are the objectives of NITI Aayog? Explain its three-years action plan.

    View answer →

  8. 2020 · Q4 · UPGS3 · 8 marks

    Explain the small-scale industries of Uttar Pradesh and discuss their role in the economy of the province.

    View answer →

More from this paper

Q1 · UPSC Mains 2021 · UPGS3 · 8 marks

Discuss the Digital India Programme of India.

Economic planning and NITI Aayog

Digital India (2015, MeitY) is the Union digital-governance and infrastructure programme. Nine pillars cover broadband, mobile, CSCs, e-Kranti, manufacturing, and jobs. BharatNet, CSC 2.0, and PMGDISHA are the last-mile connectivity and literacy rails. DigiLocker, UMANG, Aadhaar, UPI, and DBT carry documents, services, and payments. Hardware PLI and GSTN sit on the same stack; power and literacy still cap use.

Q2 · UPSC Mains 2021 · UPGS3 · 8 marks

Examine the impact of globalization on employment of formal sector of India.

Economic planning and NITI Aayog

Post-1991 opening grew formal jobs in IT, ITeS, retail, banks, and some auto and SEZ plants. SEZ Act 2005 and Make in India named the park-and-investment rails. Contract labour and fixed-term hiring informalised much factory work even when the unit was registered. EPFO, ESIC, labour codes, and Atmanirbhar Bharat Rozgar Yojana are the social-security response. Net: more white-collar formality, weaker shop-floor security.

Q3 · UPSC Mains 2021 · UPGS3 · 8 marks

How does the strategy of inclusive growth intend to meet the objectives of inclusiveness and sustainability together? Explain.

Poverty, unemployment and inclusive growth

Inclusive growth shares output with the poor and lagging regions without exhausting nature. PMJDY, DBT, MGNREGA, DAY-NRLM, PMAY, and PM-KISAN are the equity rails. Ujjwala, Jal Jeevan Mission, Swachh Bharat, National Solar Mission, PM-KUSUM, and CAMPA are the green rails. NITI SDG India Index and Aspirational Districts score both together. The strategy works only if the same household gets income and a cleaner livelihood.

Toppers' copies

Toppers' copies for this question will be uploaded soon.